63
In forceAct does not limit claimant’s other rights
Chapter 3Progress payments
Part 1Preliminary
Division 1Application and operation of chapter
63 Act does not limit claimant’s other rights
A claimant’s entitlements and remedies under this chapter do not limit—
(a)
another entitlement a claimant may have under a construction contract; or
(b)
any remedy a claimant may have for recovering the other entitlement.