77
In forceConsequences of failing to give payment schedule
Chapter 3Progress payments
Part 3Claiming progress payments
77 Consequences of failing to give payment schedule
(1)
This section applies if a respondent given a payment claim does not respond to the claim by giving the claimant a payment schedule as required under section 76.
(2)
The respondent is liable to pay the amount claimed under the payment claim to the claimant on the due date for the progress payment to which the payment claim relates.