Connection of generating plant to transmission grid or supply network only if authorised
87 Connection of generating plant to transmission grid or supply network only if authorised
A person must not connect generating plant to a transmission grid or supply network unless the person is the holder of a generation authority.Maximum penalty—5,000 penalty units.
Note—If a corporation commits an offence against this provision, each executive officer of the corporation may be taken, under section 240A, to have also committed the offence.
A person who contravenes subsection (1) may not, for the period of the contravention, take part in trading arrangements or settlement processes under this Act or the National Electricity Rules or recover payment for electricity or services provided by it.
This Act’s bill:Explanatory memorandum
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.