22
In forceElectricity entity to keep publicly controlled place in good repair after work
Chapter 2Technical requirements
Part 2Design, building and maintenance of electric lines and works
Division 5Works on publicly controlled places
22 Electricity entity to keep publicly controlled place in good repair after work
(1)
An electricity entity must keep a publicly controlled place that has been opened or broken up and restored by it in good repair—
(a)
for 3 months after restoring the place; and
(b)
if the ground subsides and continues to subside—for up to a further 9 months.
(2)
The way maintenance work is to be carried out by or for the electricity entity is as agreed between the electricity entity and the public entity that controls the place.
Research tools for this sectionSubscription
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.