202C
In forceTerm of PRCP schedule
Chapter 5Environmental authorities, PRC plans and environmentally relevant activities
Part 5Decision stage
Division 5APRCP schedules
202C Term of PRCP schedule
(1)
A PRCP schedule continues in force until the environmental authority for the relevant activities to which the PRCP schedule relates is cancelled or surrendered.
(2)
To remove any doubt, it is declared that a PRCP schedule continues in force—
(a)
in relation to a relevant activity carried out on land identified by reference to a resource tenure, even if the resource tenure expires or is cancelled; and
(b)
even if the environmental authority for carrying out a relevant activity on land to which the PRCP schedule relates is suspended under part 11 or 11A.
This Act’s bill:Explanatory memorandum
Research tools for this sectionSubscription
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.