Requirements for post-surrender management report
264A Requirements for post-surrender management report
A post-surrender management report for land the subject of a surrender application must—
be in the approved form; and
include a map of the land showing the location of—
where the resource activities were carried out on the land; and
the site features of the land; and
state—
whether the particulars of any part of the land are included in the environmental management register or contaminated land register; and
whether a site management plan under chapter 7, part 8 exists for any part of the land; and
state any assumptions made in relation to the rehabilitation or future use of the land; and
include a risk assessment of the land that complies with the residual risk assessment guideline; and
include a risk management plan for the land that complies with subsection (2) if—
the risk assessment of the land identifies residual risks for the land for which remedial action or ongoing management activities may need to be carried out in relation to the land; and
the residual risk assessment guideline requires the estimated costs and expenses that may be incurred in carrying out the remedial action or ongoing management activities to be worked out in a stated way; and
include any other matters prescribed by regulation.
A risk management plan for land the subject of a surrender application must be in the approved form and include—
spatial information about the site features of the land, including the location, size and type of the features; and
details of the consultation with affected owners and occupiers about—
any assumptions made in relation to the rehabilitation or future use of the land; and
the remedial action or ongoing management activities that may need to be carried out in relation to the land; and
a statement of any assumptions made in relation to the remedial action or ongoing management activities that may need to be carried out in relation to the land; and
an activity schedule outlining details of any remedial action or ongoing management activities that may need to be carried out in relation to the land; and
if a site management plan under chapter 7, part 8 for any part of the land provides for carrying out activities that are the same, or substantially the same, as remedial action or ongoing management activities mentioned in the activity schedule—details of how those activities are to be carried out and managed in perpetuity; and
the estimated amount of the costs and expenses that may be incurred in carrying out remedial action or ongoing management activities mentioned in the activity schedule, worked out as stated in the residual risk assessment guideline.
This provision refers to the regulations (prescribed by regulation
). Made under this Act:
- Environmental Protection (Air) Policy 2019 · Regulation
- Environmental Protection (Noise) Policy 2019 · Regulation
- Environmental Protection (Water and Wetland Biodiversity) Policy 2019 · Regulation
1 more instrument made under this Act are listed on the Act’s overview.
This Act’s bill:Explanatory memorandum
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.