287 Administering authority may request further information
(1)
After receiving an audit report for a PRCP schedule, the administering authority may, by written notice given to the holder of the schedule, ask the holder to give further information the authority requires to decide whether to take action to amend the schedule under part 6.
(2)
The request must—
(a)
be made within 10 business days after the report is received; and
(b)
state a period of at least 20 business days within which the holder must give the information.