295
In forceEnvironmental authority overrides plan
Chapter 5Environmental authorities, PRC plans and environmentally relevant activities
Part 13Plan of operations
295 Environmental authority overrides plan
(1)
This section applies if there is an inconsistency between an environmental authority and a plan of operations.
(2)
The environmental authority prevails to the extent of the inconsistency.
(3)
The holder of the environmental authority must, within 15 business days after the holder becomes aware of the inconsistency, amend the plan to remove the inconsistency.Maximum penalty—100 penalty units.