s 406ZZD

Further orders if principal contractor fails to reinstate

In force
Chapter 10AIndependent couriers
Part 5Individual courier service contracts
Division 2Unfair termination of courier service contracts

406ZZD Further orders if principal contractor fails to reinstate

(1)

If a principal contractor wilfully contravenes an order to reinstate a courier service contract for an independent courier, the commission may—

(a)

further order the principal contractor to pay the independent courier—

(i)

an amount of not more than the monetary value of 50 penalty units; and

(ii)

an amount for lost remuneration; and

(b)

make further orders until the principal contractor complies with an order under section 406ZZB or this section.

(2)

This section does not affect another provision of this Act allowing proceedings to be taken against the principal contractor.

Research tools for this sectionPro

The statute text is free to read above. View Pro plans to unlock the case-law research tools for each provision.

Section 406ZZD — Further orders if principal contractor fails to reinstate — Industrial Relations Act 2016 (Queensland) — Barrister AI