Application of div 4
318ELAU Application of div 4
This division applies if—
the overlapping tenure is a geothermal permit or GHG permit (the overlapping permit); and
the overlapping permit holder has lodged holder submissions within 4 months after the holder was given a copy of the application; and
the submissions state that the holder wishes overlapping authority priority.
However, this division does not apply if under the Geothermal Act, chapter 5 or the GHG storage Act, chapter 4, overlapping authority priority has been given for any of the relevant land.
Note—
If this subdivision does not apply, the mining lease application proceeds immediately to a decision under chapter 6, part 1 as affected by division 7.
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.