Confidentiality periods for required information for mining tenements—Act, s 382
43 Confidentiality periods for required information for mining tenements—Act, s 382
This section prescribes, for section 382(2) of the Act, the confidentiality period for the required information for a mining tenement mentioned in schedule 6, column 1.
The confidentiality period for the required information for a mining tenement starts on the day the information is lodged and ends on the day mentioned in schedule 6, column 2 opposite the required information.
There is no confidentiality period for a CSG well abandonment report under section 30 if—
the report is to be made available to a person under section 382(1)(b) of the Act; and
the person is the holder of a coal or oil shale mining tenement; and
the CSG well was drilled in the area of the person’s coal or oil shale mining tenement.
There is no confidentiality period for required information for a mining tenement not mentioned in schedule 6, column 1.