Application of div 2
79Z Application of div 2
This division applies if—
equipment or improvements are taken, constructed or placed on land in the area of a 1923 Act petroleum tenure; and
the equipment or improvements were taken, constructed or placed on the land for use for an authorised activity for the tenure; and
the tenure continues in force.
However, this division—
does not apply for a pipeline; and
Notes—
1 For the obligation to decommission pipelines, see section 75A.
2 For a general provision about ownership while a tenure is in force for a pipeline, see section 79X.
is subject to part 6O.
In this section—
equipment includes machinery and plant.
improvements—
does not include a well, water observation bore or water supply bore; but
does include any works constructed in connection with the well or bore.