Report evaluating IAR
34L Report evaluating IAR
This section applies if the Coordinator-General decides under section 34I(1)(b) to accept the draft IAR as the final IAR.
The Coordinator-General must prepare a report evaluating the IAR.
In evaluating the IAR, the Coordinator-General may—
evaluate the environmental effects of the project and any other related matters; and
state conditions under section 39, 45, 47C, 49B, 49E, 49G, 49L or 49O; and
make recommendations under section 43 or 52; and
if division 8 applies to the project—impose, under that division, conditions for the undertaking of the project.
After completing the report, the Coordinator-General must—
give a copy of the report to the proponent; and
publicly notify the report.
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.