For the purposes of the definition of major power facility in section 8(4) of the Act –
40 megawatts is the limit fixed by regulation for the new generating plant located at the power station listed as item 23 of Schedule 1 to the Act and commonly known as Tarraleah; and
40 megawatts is the limit fixed by regulation for new generating plant that generates electricity by pumping water from Lake Cethana through a pipe or tunnel to an upper reservoir, in a process also known as pumped hydro energy storage; and
300 megawatts is the limit fixed by regulation for all other forms of new generating plant.