Major project permit may be granted subject to conditions or restrictions
60ZZP Major project permit may be granted subject to conditions or restrictions
The Panel may impose conditions or restrictions on a major project permit granted under section 60ZZM(1)(a).
In addition to imposing under subsection (1) any conditions or restrictions on a major project permit that are required under subsection (4) to be imposed on a major project permit, the Panel may, subject to subsection (5), impose under subsection (1) any conditions or restrictions that, in the opinion of the Panel, are necessary or desirable for the effective and appropriate use or development of land.
In deciding whether to impose under subsection (1) conditions or restrictions on a major project permit to be granted in relation to the major project, the Panel must consider – the conditions and restrictions that a participating regulator requested, in a final advice under section 60ZZF(1), the Panel to impose on a major project permit in relation to the project; and any representations made under section 60ZZD(1) in relation to such conditions or restrictions; and any matters raised in hearings in relation to the major project.
The Panel must, under subsection (1), impose on a major project permit granted under section 60ZZM(1)(a) any conditions or restrictions that a participating regulator that is a relevant regulator in relation to the Aboriginal Heritage Act 1975 or the Threatened Species Protection Act 1995, requests the Panel, in a final advice under section 60ZZF(1), to impose on the permit.
The Panel must not impose on a major project permit a condition or restriction that is inconsistent with a condition or restriction that the Panel must, under subsection (4), impose.
The conditions that may be imposed on a major project permit include, but are not limited to including, a condition that all reasonable steps must be taken to enter into an agreement in respect of a use or development forming all or part of the project to which the permit relates.
If a condition referred to in subsection (6) is imposed on a major project permit, the Panel must specify on the major project permit the matters, and the requirements in respect of those matters, to be included in the agreement.
If – a person is granted a major project permit on which is imposed a condition, referred to in subsection (6), that all reasonable steps must be taken to enter into an agreement; and that person is not the owner of all of the land in respect of which the agreement must be entered into – the Panel must, within 7 days of granting the permit, serve on each other owner of the land notice of the Panel's decision to impose the condition.
If a condition or restriction is imposed under subsection (1) on a major project permit in accordance with subsection (4), the Panel must designate on the permit the relevant regulator, or relevant regulators, if any, that has or have the responsibility under section 60ZZZD(4) for the enforcement of the condition or restriction.
Without limiting the conditions or restrictions that may be imposed under subsection (1) on a major project permit otherwise than in accordance with subsection (4), such a condition or restriction may specify that – plans, information, designs, or other documents, are required, under the condition or restriction, to be prepared and provided to the Panel or a planning authority; and particular actions or works are to be carried out to the satisfaction of the Panel or a planning authority – and, if such a condition or restriction refers to the Panel, then, after the major project permit has taken effect, the reference in the condition or restriction to the Panel is taken to be a reference to the Commission.