For the purposes of section 8(1)(b) of the Act, the following information is prescribed as the information that is to be contained in a report to the Minister from the proponent of a project:an executive summary of the project; an outline of the project as specified in subregulation (2); a proposed timetable for the project as specified in subregulation (4); an assessment of the public benefits of the project including – the details of the matters to be considered in determining whether or not it is in the public interest for the project to be declared a major infrastructure project in accordance with the Act; and the details of potential social, economic and environmental impacts associated with the project that the proponent considers relevant to the determination; details of the consultation that has been undertaken with stakeholders and the outcome of that consultation; if consultation under paragraph (e) has taken place and further consultation is planned, an outline of such consultation with respect to relevant matters specified in subregulation (4)(a), (b), (c), (d), (e), (f) and (g).
For the purposes of subregulation (1)(b), an outline of a project is to include, where appropriate, the following information:background of the proponent of the project including details of experience and financial capacity to undertake the project and details as to where the proponent may be contacted; the purpose of the project; a description of the proposed project including a description of – each use or development comprised in the project; and all proposed major buildings, structures, equipment, infrastructure and ancillary facilities comprised in the project; and the proposed ongoing operations associated with the project; the level of investment that will be required to establish the project; details of – legislation of this State, and of the Commonwealth, that is relevant to the project; and State policy, within the meaning of the State Policies and Projects Act 1993, relevant to the project; details of the proposed geographical location of the project, including – details of the municipal areas and municipal boundaries relevant to the project; and an outline of constraints analysis and alternative route investigations undertaken, if any, by the proponent; a statement as to whether a corridor is required and the proposed width of the corridor; a statement as to whether the proponent of the project wishes the Crown to acquire and sell to the proponent land for the purposes of the project and, if so, details, to the extent known, of the land likely to be required; details of land or easements, including construction and corridor access easements, that must be acquired in order for the project to proceed; a general description of the physical environment that may potentially be affected by the project including landforms, waterways, land uses, existing infrastructure, flora, fauna and heritage values; a general description of the social and economic environment that may potentially be affected by the project.
For the purposes of subregulation (1)(b), the outline of the project is to be supported, where appropriate and relevant, with maps, schematic diagrams, aerial photographs and computer-aided representations.
For the purposes of subregulation (1)(c), the proposed timetable for the project is to include details of the timing of – project planning and data collection relating to environmental issues and any other issues; and community consultation over the whole course of the project; and surveys required to define the corridor; and land acquisition required for the project; and discrete stages in the development of the project, if relevant; and construction and post-construction rehabilitation; and completion of the project.