reg 7
In forceThermal waste to energy processes
Part 2Advanced recycling process, cap limit, exempt waste, thermal waste to energy processes and permitted waste
7 Thermal waste to energy processes
For the purposes of section 74M(2)(f) of the Act, a thermal waste to energy process does not include the following—
(a)
a thermal waste to energy process in respect of which a pilot project licence has been issued and is in force;
(b)
a process that treats waste biomass through a pyrolysis process or gasification process to sequester carbon.
Example
A process that produces biochar that is applied to land.