Noise limit
131BA Noise limit
Subject to subregulations (2) and (3), the noise limit for a wind energy facility must be determined in accordance with the relevant noise standard for that facility.
If a wind energy facility is the subject of a wind turbine noise agreement, the noise limit for that facility in relation to noise emissions to the premises of the relevant landowner is—
if the agreement is made before 1 November 2021, the noise limit specified in the agreement; or
if the agreement is made on or after 1 November 2021, the noise limit that is the greater of—
45 dB(A); or
the background sound level plus 5 dB.
The noise limit for a 1998 NZS wind energy facility may be determined in accordance with the procedures set out in NZS 6808:2010 that relate to extraneous noise.
Reg. 131BB inserted by S.R. No. 120/2022 reg. 7.