56S
In forceUtility liable for differential if it requests upgrade
Part 2BLink Upgrade Project
Division 7Interface with Utilities
Subdivision 6Liability for costs
56S Utility liable for differential if it requests upgrade
S. 56S inserted by No. 81/2006 s. 72.
If a Utility requests that a higher standard than the standard required by section 56R should apply to the relocation or rectification of Utility infrastructure, the Utility is liable to pay the difference in cost between the lower and higher standard.
Research tools for this sectionSubscription