Schedule 5A.1, s 10.2
In forceAfter clause 6.12.1(20) of the National Electricity Rules insert—
Schedule 5A.1Minimum content requirements for connection contract
Part BConnection offer involving embedded generation
10.2 After clause 6.12.1(20) of the National Electricity Rules insert—
"(21) a decision on the connection policy that is to apply to the Distribution Network Service Provider for the regulatory control period (which may be the connection policy as proposed by the Distribution Network Service Provider, some variant of it, or a policy substituted by the AER).".
11 Clause 6.12.3—Extent of AER's discretion in making distribution determinations