Division 3—Registration of a major hazard facility
515Registration of a major hazard facility
(1)
Subject to subregulation (2), the Authority, within 90 days of receipt of an application for registration of a major hazard facility, must register the facility as a major hazard facility.
(2)
Subregulation (1) does not apply if the Authority is satisfied that the applicant does not intend to operate a major hazard facility.
Example
If the applicant has registered the facility several times without ever obtaining a major hazard facility licence then the Authority may be satisfied that the applicant does not intend to operate a major hazard facility.