Effect of Order
132 Effect of Order
While an Order under section 131 is in effect—
a permit that was granted under this Act before the Order took effect in relation to the land the subject of the Order is of no force or effect; and
a building permit that was issued before the Order took effect in relation to the land the subject of the Order is of no force or effect; and
a responsible authority must refuse to grant a permit under this Act in relation to the land the subject of the Order; and
a relevant building surveyor must refuse a building permit in relation to the land the subject of the Order.
Subsection (1)(a) and (c) do not apply in relation to a permit or the grant of a permit under this Act for a use or development that is specified in the Order under section 131(1)(b) or (c) as an exception.
Subsection (1)(b) and (d) do not apply in relation to a building permit or the issue of a building permit for building work in respect of a development that is specified in the Order under section 131(1)(b) as an exception.
A permit granted in contravention of subsection (1)(c) is invalid and of no force or effect.
A building permit issued in contravention of subsection (1)(d) is invalid and of no force or effect.