(1)A licensed surveyor making a cadastral survey must—
(a)adopt and verify a datum in accordance with a previous cadastral survey or plan; and
(b)if an abstract of field records is to be lodged with the Surveyor-General or the Registrar, bring the bearing datum of the survey on to MGA2020; and
(c)if the height of a boundary is to be determined, relate the height of the boundary to AHD71 and properly verify the connection; and
(d)if the position of the subject land is shown by a connection, measure that connection unless the position of the subject land has been satisfactorily determined in previous surveys; and
(e)connect the cadastral survey to relevant permanent marks, primary cadastral marks, pegs and other survey marks; and
(f)locate and clearly describe any feature on or near the boundaries of the subject land likely to affect those boundaries; and
(g)locate and clearly describe any feature within the subject land the description and position of which is necessary for the purpose of the survey; and
(h)determine the length, bearing and, if applicable, height of each surveyed boundary of the subject land and independently check the accuracy of each determination.
(2)A licensed surveyor making a cadastral survey must ensure that an irregular boundary is determined at all conspicuous changes in direction at such intervals as are necessary to accurately determine the boundary.
(3)A licensed surveyor making a cadastral survey must connect the cadastral survey to at least 3 permanent marks or primary cadastral marks in the immediate vicinity of the subject land, and—
(a)if there are less than 3 permanent marks or primary cadastral marks in the immediate vicinity of the subject land, place further permanent marks or primary cadastral marks such that there is a minimum of 3 permanent marks or primary cadastral marks to which the cadastral survey connects; and
(b)if there are more than 10 allotments or lots at ground level, place further permanent marks or primary cadastral marks within the subdivision of the subject land so that the distance between those marks is not greater than—
(ii)an alternate distance approved by the Surveyor‑General; and
(c)if more than 4 permanent marks or primary cadastral marks are required to be placed under paragraph (b), ensure that one in every 5 marks is a permanent mark; and
(d)if the design or layout of a subdivision of the subject land is unusual, place additional permanent marks or primary cadastral marks within the subdivision as is reasonable in the circumstances.
(4)If a licensed surveyor connects the survey of a subdivision of the subject land to a minimum of 3 permanent marks or primary cadastral marks in situations where the marks are unlikely to be disturbed, the licensed surveyor may postpone the placement of any further permanent marks or primary cadastral marks within the subdivision if the construction of roads or buildings or other works are to be undertaken which are likely to displace those permanent marks or primary cadastral marks during construction.
(5)A licensed surveyor who postpones the placement of further marks under subregulation (4) must lodge with the Registrar a supplementary abstract of field records showing the particulars and connections to the marks placed, within 45 days after the construction is completed.