s 87

Requirement for building or demolition permit not affected by court order

In force
Part 6Work affecting other land
Division 3Obtaining consent or court orders to affect other land

87 Requirement for building or demolition permit not affected by court order

(1)

An order under section 86(2) that allows building or demolition work to be done without the consent of an owner of the affected land does not affect a requirement under section 9 or 10 for a building permit or demolition permit to be in effect for the work.

(2)

If —

(a)

an order is made under section 86(2)(c) for the placement of a protection structure into or onto land beyond the boundaries of the works land; but

(b)

an application for a building permit for the placement of the protection structure is not made within 30 days of the order,

the person responsible for work on the works land may apply for a building permit for the placement of the protection structure, and for that purpose section 16(b) applies as if the application must be signed by that person instead of each owner of the land into or onto which the protection structure is proposed to be placed.