Notice‑based time bar has no effect if declared unfair in particular case
16 Notice‑based time bar has no effect if declared unfair in particular case
In this section —
notice includes notice of the actual or estimated time or cost for doing a thing, notice of intention to do a thing, notice of the description of a thing or notice of any other kind;
notice‑based time bar provision, of a construction contract, means a provision of the contract that makes any of the following contingent on the provision of notice by a party to the contract —
an entitlement to payment for construction work carried out or undertaken to be carried out, or for related goods and services supplied or undertaken to be supplied, under the contract;
an extension of time for doing a thing that affects an entitlement referred to in paragraph (a).
A notice‑based time bar provision of a construction contract may be declared under this section to be unfair in the case of a particular entitlement under the contract if compliance with the provision in that case —
is not reasonably possible; or
would be unreasonably onerous.
A notice‑based time bar provision of a construction contract may be declared to be unfair by —
an adjudicator or review adjudicator for the purposes of adjudication proceedings under this Act in relation to the contract; or
a court for the purposes of proceedings for the recovery of money or enforcing other rights under the contract; or
an arbitrator for the purposes of arbitration proceedings under the contract or under any separate agreement between the parties; or
an expert appointed by the parties for the purposes of proceedings to determine a matter under the contract.
A notice‑based time bar provision of a construction contract that is declared to be unfair has no effect in the case of the particular entitlement that is the subject of the proceedings in which it was declared unfair, but continues to have effect in other circumstances or challenges arising under the same or a related contract.
The party in any proceedings who alleges that a notice‑based time bar provision is unfair bears the onus of establishing that it is unfair.
In determining whether a notice‑based time bar provision is unfair, the adjudicator, review adjudicator, court, arbitrator or expert must take the following into account —
when the party required to give notice would reasonably have become aware of the relevant event or circumstance, having regard to the last day on which notice could have been given;
when and how notice was required to be given;
the relative bargaining power of each party in entering into the construction contract;
the irrebuttable presumption that the parties have read and understood the terms of the construction contract;
the rebuttable presumption that the party required to give notice possesses the commercial and technical competence of a reasonably competent contractor;
if compliance with the provision is alleged to be unreasonably onerous — whether the matters set out in the notice are final and binding;
any matter prescribed by the regulations for the purposes of this paragraph.
In determining whether a notice‑based time bar provision is unfair, the adjudicator, review adjudicator, court, arbitrator or expert must not take into account the provisions of any related contract or the things that happened under any related contract.