Due date for payment
20 Due date for payment
A progress payment (other than for home building work) becomes payable —
in the case of a progress payment to be made by a principal to a head contractor — on the date that is 20 business days after a payment claim is made under Part 3 for the progress payment; or
in the case of a progress payment to be made to a subcontractor — on the date that is 25 business days after a payment claim is made under Part 3 for the progress payment.
Note for this subsection:
The due date for payment by a principal when there is no head contractor is 25 business days after the payment claim is made as provided by paragraph (b) — see definitions of head contractor and subcontractor in section 4(1).
However, if the construction contract provides that the progress payment becomes payable on an earlier date than that provided by subsection (1), the progress payment becomes payable on that earlier date.
A progress payment for home building work becomes payable —
if the construction contract provides for the matter — on the date determined in accordance with the contract; or
if the construction contract does not provide for the matter — on the date that is 10 business days after a payment claim is made under Part 3 for the progress payment.
Note for this section:
Section 14(2) provides that a pay when paid provision in a construction contract has no effect.