Consequences of not paying claimed or scheduled amount
27 Consequences of not paying claimed or scheduled amount
In this section —
claimed or scheduled amount owed, in relation to a payment claim, means —
if the respondent did not respond to the payment claim by giving a payment schedule to the claimant within the time allowed for the response — the claimed amount under the payment claim; or
if the respondent did respond to the payment claim by giving a payment schedule to the claimant within the time allowed for the response and the payment schedule indicates the scheduled amount that the respondent proposes to pay to the claimant — that scheduled amount.
If a claimant makes a payment claim for a progress payment and the respondent does not pay the claimed or scheduled amount owed to the claimant in full on or before the due date for the progress payment, the claimant may do either but not both of the following —
recover from the respondent the unpaid portion of the claimed or scheduled amount owed as a debt due to the claimant in a court of competent jurisdiction;
make an adjudication application in relation to the payment claim.
Notes for this subsection:
1. Division 7 provides that in addition to taking debt recovery action or making an adjudication application, the claimant may suspend work or supply under the construction contract.
2. If no payment is proposed in a payment schedule, the claimant cannot commence proceedings in a court under this section, but may make an adjudication application.
If the claimant commences proceedings under this section in a court of competent jurisdiction to recover from the respondent the unpaid portion of the claimed or scheduled amount owed —
judgment in favour of the claimant is not to be given unless the court is satisfied that the relevant circumstances exist; and
the respondent is not, in those proceedings, entitled —
to bring any cross‑claim against the claimant; or
to raise any defence in relation to matters arising under the construction contract.
The relevant circumstances for the purposes of subsection (3)(a) are as follows —
the respondent —
did not respond to the payment claim by giving a payment schedule to the claimant within the time allowed for the response; or
did respond to the payment claim by giving a payment schedule to the claimant within the time allowed for the response, and the payment schedule indicates the scheduled amount that the respondent proposes to pay to the claimant;
the respondent has not paid the claimed or scheduled amount owed to the claimant in full on or before the due date for the progress payment;
if the payment of the claimed or scheduled amount owed is dependent on the substitution of performance security under Division 6 — the requisite compliant performance bond has been duly executed by an authorised issuing institution as referred to in that Division.