Adjudicator’s determination
38 Adjudicator’s determination
The adjudicator must determine —
the amount of the progress payment, if any, to be paid by the respondent to the claimant; and
the due date for the payment of that amount under section 20; and
the rate of interest payable on that amount under section 21; and
if no amount of progress payment is required to be paid — that no amount is payable.
Notes for this subsection:
1. Part 4 provides that the adjudicator may also determine that an amount of money is to be paid out of a retention money trust account under that Part.
2. Division 4 provides that the adjudicator is to determine the amount of adjudication fees and expenses payable to the adjudicator and the proportion of the amount for which each party is liable.
3. Sections 58 and 59 provide that a determination may require the release of performance security or the substitution of performance security that is proposed in a payment claim.
In determining an adjudication application, the adjudicator may consider only the following matters —
this Act and the regulations;
the relevant construction contract;
the relevant payment claim and the adjudication application, together with submissions (including accompanying documents) duly made by the claimant in support of the claim and application;
the relevant payment schedule and adjudication response (if any), together with submissions (including accompanying documents) duly made by the respondent in support of the schedule and response;
any further submissions of the claimant or respondent (including accompanying documents) requested by the adjudicator;
the outcome of any conference of the parties called by the adjudicator;
the results of any inspection carried out or testing arranged by the adjudicator;
any expert report obtained by the adjudicator.
In determining an adjudication application, the adjudicator must not consider the following matters —
an adjudication response that is given after the time allowed by this Division;
any reasons included in an adjudication response for withholding payment that cannot under this Division be included in the adjudication response because those reasons were not included in the payment schedule;
any submissions (including accompanying documents) made to the adjudicator that are not authorised to be made under this Division or that contravene any other limitation prescribed by the regulations on the submissions that may be made.
The adjudicator’s determination must —
be made in writing and be in the approved form (if any); and
include the reasons for the determination; and
be given by the adjudicator to the claimant, respondent and Building Commissioner.
Subsection (6) applies if the adjudicator (or any other adjudicator or review adjudicator) has, for the purposes of a previous determination, calculated —
the value of any construction work carried out under a construction contract; or
the value of any related goods and services supplied under a construction contract.
The adjudicator is, in a subsequent determination that involves calculating the value of construction work or related goods and services referred to in subsection (5), to give the work or related goods and services the same value as that previously calculated unless the claimant or respondent satisfies the adjudicator that the value has changed since the previous calculation.
The adjudicator may, on the adjudicator’s own initiative or on the application of the claimant or respondent, correct the adjudicator’s determination if it contains —
a clerical mistake or defect of form; or
an error arising from an accidental slip or omission; or
a material arithmetic error or a material mistake in the description of any person, thing or matter.