Requirements relating to adjudication review application
42 Requirements relating to adjudication review application
An adjudication review application —
must be made in writing and be in the approved form (if any); and
must be accompanied by a copy of the following —
the construction contract or the relevant provisions of the construction contract;
the payment claim;
the payment schedule (if any);
the adjudication application;
the adjudication response (if any);
any submissions made to the adjudicator by the claimant or respondent (including accompanying documents);
the adjudicator’s determination;
and
must be accompanied by the application fee (if any) determined by the authorised nominating authority to which the adjudication review application is made; and
may contain submissions relevant to the application that the claimant or respondent making the application chooses to include.
The claimant or respondent cannot include any reasons for a matter in the adjudication review application unless those reasons were raised in the original adjudication being reviewed.
The claimant or respondent making the adjudication review application must give a copy of the application (and of any accompanying documents) to the other party within 1 business day after the application is made.
The regulations may prescribe the maximum application fee that an authorised nominating authority may determine under this section (including different maximum amounts depending on the amount of the payment claim or on other specified factors).
Note for this section:
Under Division 4 the authorised nominating authority or review adjudicator may require the payment of a deposit or security for the estimated adjudication fees and expenses of the review adjudicator.
Sign in to see bill, explanatory material, and regulations and instruments
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.