Claimant’s right to suspend work or supply for non‑payment
62 Claimant’s right to suspend work or supply for non‑payment
A claimant may suspend carrying out construction work, or supplying related goods and services, under a construction contract if the claimant makes a payment claim for a progress payment and —
the respondent does not pay the claimed or scheduled amount owed (as defined in section 27(1)) to the claimant in full on or before the due date for the progress payment; or
the respondent does not pay the adjudicated amount in full as required by section 52; or
the respondent fails to pay any retention money relating to the progress payment into a retention money trust account as required by Part 4.
A claimant cannot suspend work or supply under subsection (1)(b) while an adjudication review application made by the respondent has not been determined.
A claimant cannot suspend work or supply unless —
the claimant has given the respondent written notice of the claimant’s intention to suspend work or supply under the construction contract; and
at least 2 business days have passed since the claimant gave that notice.
A notice of intention to suspend work or supply must state that it is given under this Act.
The right to suspend work or supply conferred by subsection (1)(a) or (b) continues until 3 business days have passed since the claimant received the amount payable by the respondent.
The right to suspend work or supply conferred by subsection (1)(c) continues until —
the respondent pays the retention money into a retention money trust account and notifies the claimant that the retention money has been paid into the account; and
3 business days have passed since the claimant was so notified.
A right under this Division to suspend work or supply is in addition to the rights conferred by this Act to recover a claimed or scheduled amount owed (as defined in section 27(1)), to enforce payment of an adjudicated amount or to require payment of retention money into a retention money trust account.
Sign in to see bill, explanatory material, and regulations and instruments
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.