Post‑closure plan
17 Post‑closure plan
The occupier of a landfill site must prepare and submit to the Chief Executive Officer for approval a post‑closure rehabilitation plan, in accordance with subregulation (2), for the site within 18 months of the site being registered under regulation 5B of the Environmental Protection Regulations 1987.
Penalty: $5 000.
A post‑closure rehabilitation plan is to set out a plan for the rehabilitation of the site after it has ceased to be a landfill site and, in particular, is to specify —
options for the use of the site after it has ceased to be a landfill site, and is to specify the preferred option;
a conceptual design of the infrastructure needed for the preferred option for the use of the site after it has ceased to be a landfill site;
the estimated final contours of the site, after allowing for settlement, and specifying to what extent settlement has been allowed for;
the capping materials proposed to be used on the site;
a proposed system of drainage of the site;
measures proposed for the protection of the environment and the monitoring of the site; and
the estimated period for which the site will require protection and monitoring.