FORCE MAJEURE
18 FORCE MAJEURE
In this Agreement force majeure means events or occurrences and the effects of them beyond the reasonable control of the party claiming force majeure which affects the ability of that party to observe and perform its obligations under this Agreement, and includes war, invasion, riot, civil or military disturbances, sabotage, strikes, picketing or other labour disputes or disturbances, expropriation, lightning, fire, flood or threats of floods, earthquake, storm, cyclone, explosion, governmental restrictions or other governmental actions or inactions (unless such restrictions, actions, or inactions arise out of the failure of the party affected to comply with any governmental requirement), and orders or temporary or permanent injunctions of any duly constituted court of competent jurisdiction or any duly authorised administrative agency or officer (unless any such order or injunction was imposed by reason of the failure of the party affected to observe and obey any legal requirement or obligation under this Agreement), but does not include inability to obtain finance on acceptable terms.
If any party is unable, wholly or in part, by reason of force majeure to carry out any obligation on it, and notifies the other party that it wishes to claim that it is affected by force majeure, the obligation shall be suspended so far as it is affected by the force majeure during the period from the giving of the notice that force majeure is claimed until the force majeure and the effects of the force majeure cease. The notice claiming force majeure shall contain the particulars of the force majeure, and so far as is known, the extent to which the party claiming force majeure considers that it will be unable to perform or be delayed in performing its obligations.
A party affected by force majeure shall take all reasonable steps to remedy or remove the force majeure and the effect of it as quickly as possible.
Where a party gives a notice pursuant to this clause it shall thereafter during the continuance of the force majeure at least every five days give notice to the other party of the then probable extent to which it will be unable to perform or be delayed in performing its obligations and of any significant changes relative to the force majeure since it gave its last notice to the other party.
The statute text is free to read above. View subscription options to unlock the case-law research tools for each provision.