Independent competent persons must review work involving dam design
24 Independent competent persons must review work involving dam design
The owner of an extreme or high consequence dam, other than a high C consequence dam, must ensure that relevant design work for the dam is reviewed by a panel of at least 2 independent competent persons.
The owner of a high C consequence dam must ensure that relevant design work for the dam is reviewed by an independent competent person.
In this clause—
independent competent person for a review of work means a person who—
has not been involved in the work, and
is independent of each person who has carried out the work.
relevant design work for a dam means—
work involving designing the dam, or
work involving designing a major modification to the dam.