7H Conditions of scheme approval
Without limiting section 7G, conditions of a scheme approval imposed by the regulations or by IPART may require the following—
completion of the construction of the infrastructure in accordance with specified plans and specifications,
the giving and maintaining of security, in an amount and form determined by IPART, for compliance with the conditions of approval and the completion of the construction of the infrastructure,
the maintaining of insurance of a type and at a level specified in the condition,
the completed infrastructure to meet specified criteria for safe and reliable operation and the protection of the environment and public health,
the installation of individual meters for each household or business,
the testing, certification or auditing of the infrastructure,
the submission to IPART of notifications relating to the infrastructure,
the preparation of plans or systems for operation of the scheme.
A registered operator constructing water industry infrastructure to which this Part applies must—
comply with the conditions of the relevant scheme approval, and
ensure compliance with the conditions by other persons who are engaged by or act on behalf of the registered operator or for whom the registered operator is otherwise responsible in connection with the construction of the infrastructure.
Maximum penalty—
for a corporation—18,000 penalty units, or
for an individual—3,500 penalty units.
This provision refers to the regulations (the regulations
). Made under this Act:
This Act’s bill:Explanatory memorandumSecond reading speech