27A Lapsing of declaration if EIS required
(1)
This section applies to a coordinated project if an EIS is required for the project.
(2)
The declaration for the project lapses if, within 18 months of the terms of reference being finalised, the Coordinator-General has not, under section 34A(1)(b), accepted a draft EIS for the project as the final EIS.
(3)
Despite subsection (2), if before the declaration lapses, the Coordinator-General gives written notice to the proponent stating a later time for the declaration to lapse, the declaration does not lapse until the later time.