27B Lapsing of declaration if IAR required
(1)
This section applies to a coordinated project if an IAR is required for the project.
(2)
The declaration for the project lapses if, within 18 months of the declaration being made, the Coordinator-General has not, under section 34I(1)(b), accepted a draft IAR as the final IAR for the project.
(3)
However, if before the lapsing of the declaration under subsection (2), the Coordinator-General gives written notice to the proponent stating a later time for the declaration to lapse, the declaration does not lapse until the later time.