Criteria for decision
54W Criteria for decision
This section applies to the Coordinator-General in deciding whether to issue an environmental approval for the coordinated project or impose conditions on the approval.
The Coordinator-General must—
consider all of the following—
the impacts the project has had, will have or is likely to have, on each environmental matter protected by a specified provision;
any criteria for the decision prescribed by regulation;
the protected matters report;
any further information provided under a notice under section 54S(2);
any information, advice or comment given under section 54S(6);
all accepted submissions for the project; and
ensure the approval and conditions are not inconsistent with the bilateral agreement.
Also, the Coordinator-General may consider—
the proponent’s environmental record; and
any other matter the Coordinator-General considers relevant.
The Coordinator-General must prepare a report (an assessment report) that—
demonstrates the Coordinator-General’s consideration of the matters mentioned in subsections (2) and (3); and
identifies the information and opinions, and the source of the information and opinions, on which the consideration is based.
This provision refers to the regulations (prescribed by regulation