54Y
CurrentIssuing environmental approval
Part 4AAssessment and approval of particular coordinated projects under bilateral agreement
Division 3Assessment and approval process
54Y Issuing environmental approval
(1)
If the Coordinator-General’s decision under section 54T is to approve the undertaking of all or part of the coordinated project, the Coordinator-General must issue an environmental approval to the proponent.
(2)
The environmental approval must state each of the following—
(a)
the proponent’s name;
(b)
the project, or part of the project, for which the approval is given;
(c)
each specified provision for which the approval is given;
(d)
the period for which the approval has effect;
(e)
the conditions of the approval;
(f)
for each condition—the nominated entity with jurisdiction for the condition.