Report on installation of separate meters on properties
99 Report on installation of separate meters on properties
The Commission must undertake a cost benefit analysis of implementing a scheme designed to ensure, so far as is reasonably practicable, that—
all land—
that is owned by the South Australian Housing Trust or another agency or instrumentality of the Crown; and
that is used for residential purposes; and
that is supplied with water by a water industry entity as part of a reticulated water system; and
any other land the Commission determines to include in the analysis, will have a meter that records the amount of water supplied to that piece of land.
The scheme for the purposes of the analysis must address—
the fitting of meters to premises existing at the time of the publication of the report (insofar as meters are not fitted); and
the fitting of meters to premises constructed after the publication of the report.
The Commission must prepare and publish a report on the analysis by
30 June 2013.