Time limits relating to the report or consent of reporting authorities
34 Time limits relating to the report or consent of reporting authorities
For the purposes of clause 6(1), (2) and (3) of Schedule 2 to the Act, the prescribed time is—
in the case of an application relating to a Class 1 or 10 building—
for a matter under Division 2 of Part 5 or regulation 89, within 15 business days after a reporting authority is given an application for a building permit by the relevant building surveyor; and
in all other cases, within 10 business days after a reporting authority is given an application for a building permit by the relevant building surveyor; or
in the case of an application relating to any other class of building—
for a matter referred to the chief officer, within 15 business days after the chief officer is given an application for a building permit by the relevant building surveyor; and
in all other cases, within 10 business days after a reporting authority is given an application for a building permit by the relevant building surveyor.
For the purposes of clause 6A(2), (3) and (4) of Schedule 2 to the Act, the prescribed time is 15 business days after the reporting authority receives a copy of the application for the building permit.