s 24

Notice of decision not to grant building or demolition permit

In force
Part 2Building and demolition permits
Division 2Applications for building or demolition permits

24 Notice of decision not to grant building or demolition permit

A permit authority must —

(a)

record the grounds on which a decision to refuse to grant a building permit or demolition permit is based, and the reasons for the decision; and

(b)

as soon as is practicable, but in any case not later than 5 days after making the decision, give to the person to whom the decision relates written notice of the decision, together with those grounds and reasons, and the person’s right of review under section 119.