reg 10

Notification after completion of work

In force
Part 2Sanitary plumbing and sanitary drainage

10 Notification after completion of work

(1)

This section applies if—

(a)

sanitary plumbing or sanitary drainage work has been inspected and approved; or

(b)

an inspector has advised the person who did the work that an inspection is not required.

(2)

A person who does sanitary plumbing or sanitary drainage work must, if satisfied that the work has been completed in accordance with this regulation and the plumbing code, within 7 days after completion of the work, give the construction occupations registrar—

(a)

a statement of the work completed; and

(b)

evidence of payment of inspection fees under this regulation; and

(c)

a copy of—

(i)

if the work relates to a single residential building—a drainage plan on which there is endorsed a certificate that the plan is a true record of the work carried out; or

(ii)

in any other case—an approved drainage plan on which there is endorsed a certificate that the plan is a true record of the work carried out.

Note A certificate of compliance for plumbing or sanitary drainage work cannot be issued under s 25 unless the construction occupations registrar is satisfied that the work complies with this regulation. The registrar may only be able to be so satisfied if the statement, evidence and plan about the work has been given.