reg 7B
In forceNo reconsideration for plan amendment—Act, s 9 (3)
Part 2Sanitary plumbing and sanitary drainage
7B No reconsideration for plan amendment—Act, s 9 (3)
(1)
A proposed amendment to a plan does not require reconsideration of the plan approval if the only amendment to the plan is to the length and alignment of pipework only.
(2)
However, subsection (1) does not apply if the amendment would—
(a)
change the point of connection of the pipework to an outlet, fixture or appliance; or
(b)
change the point of connection of the pipework to a sewage network or its primary water supply; or
(c)
increase the branching of the pipework; or
(d)
add a run of pipework not shown in the plan.
Research tools for this sectionPro
The statute text is free to read above. View Pro plans to unlock the case-law research tools for each provision.