s 45
In forceProject proponent must notify Authority if major project is abandoned or cancelled
Part 3Notification obligations
Division 1Major projects
45 Project proponent must notify Authority if major project is abandoned or cancelled
(1)
If a major project is abandoned or cancelled, the project proponent for the project must:
(a)
notify the Authority of the abandonment or cancellation; and
(b)
do so within 60 days after the project is abandoned or cancelled.
(2)
A notification under subsection (1) must:
(a)
be in a form approved, in writing, by the Authority; and
(b)
be accompanied by such information as is specified in the legislative rules.