301
In forceSafe work method statement – copy to be given to principal contractor
Chapter 6Construction Work
Part 6.3Duties of Person Conducting Business or Undertaking
Division 2High risk construction work – safe work method statements
301 Safe work method statement – copy to be given to principal contractor
A person conducting a business or undertaking that includes carrying out high risk construction work in connection with a construction project must, before the high risk construction work commences, ensure that a copy of the safe work method statement for the work is given to the principal contractor.
In the case of – an individual, a fine not exceeding $3 600; or a body corporate, a fine not exceeding $18 000.