reg 241

Testing of underground consumer's mains

In force
Part 2Electrical installations
Division 10Testing of electrical installation work

241 Testing of underground consumer's mains

(1)

For the purposes of section 44(1)(b) of the Act, if underground consumer's mains are installed for the first time, the insulation resistance of the consumer's mains that were installed must be tested to verify that the consumer's mains comply with regulation 228(1) after the work is completed and before certification or inspection of the work under the Act.

(2)

For the purposes of section 44(1)(b) of the Act, if electrical installation work is carried out on existing underground consumer's mains, the insulation resistance of the consumer's mains that were subject to the work must be tested to verify that the consumer's mains comply with regulation 228(2) after the work is completed and before certification or inspection of the work under the Act.

Research tools for this sectionPro

The statute text is free to read above. View Pro plans to unlock the case-law research tools for each provision.