reg 245
In forceTesting of grid-connected inverter energy systems
Part 2Electrical installations
Division 10Testing of electrical installation work
245 Testing of grid-connected inverter energy systems
If electrical installation work includes electrical work on a grid-connected inverter energy system, the licensed electrical installation worker carrying out that work must ensure that the electrical installation work is tested after the work is completed and before it is placed into service to verify the following—
(a)
that the inverter energy system takes longer than 60 seconds to connect to the distribution network after the installation's main switch is closed;
(b)
that the inverter energy system disconnects from the distribution network in less than 2 seconds after the installation's main switch is opened.
Penalty: 20 penalty units.