Duration of building or demolition permit

In force
Part 2Building and demolition permits
Division 4Duration of building or demolition permits

32 Duration of building or demolition permit

(1)

A permit has effect for —

(a)

the period set out in the permit as the period during which it has effect; or

(b)

such longer period that is approved on an application to extend the time during which the permit has effect.

(2)

If a permit does not set out the period during which it has effect, a permit has effect for —

(a)

2 years from the day on which it is granted; or

(b)

such longer period that is approved on an application to extend the time during which the permit has effect.

(3)

The regulations may provide for —

(a)

applications to extend the time during which a permit has effect; and

(b)

the submission of information and documentation in support of an application; and

(c)

the grounds for extending the time during which a permit has effect; and

(d)

the maximum period of extension of time during which a permit can have effect; and

(e)

the imposition of conditions in relation to an extension of time; and

(f)

fees for applications; and

(g)

review by the State Administrative Tribunal of a decision of a permit authority made on an application; and

(h)

any other matter relating to an application.

(4)

A permit ceases to have effect on the day on which a notice of completion in relation to the permit is received by the permit authority under section 33.