33
In forceNotice of completion
Part 2Building and demolition permits
Division 4Duration of building or demolition permits
33 Notice of completion
(1)
The responsible person in relation to a permit must, within 7 days of completion of the work, or the stage of the work, for which the permit was granted, give notice of completion to a relevant permit authority.
Penalty: a fine of $10 000.
(2)
A notice of completion must —
(a)
be in an approved form; and
(b)
state that the work, or the stage of the work, for which the permit was granted, is completed; and
(c)
be accompanied by a copy of a certificate for each inspection or test mentioned in section 25(3)(h) or (4)(f) that applies to the permit.