s 1
In forcea new high temperature kiln. This will double the drying capacity and will operate 24 hours per day on a 7 day week basis;
1 a new high temperature kiln. This will double the drying capacity and will operate 24 hours per day on a 7 day week basis;
2. a new debarker, which will be part of a new scanner/sorter line. The new line will operate on a single shift, and debark and scan logs in order to determine the input volume for payment purposes; and
3. a new moulder with input and output conveyors as necessary to allow the upgrading of the surface finish on furniture grade timber.
The green mill and dry mill will operate on a two shift basis, while the high temperature kilns will operate continuously.
Second Stage
This will increase annual log input capacity by 50,000 m3 up to 200,000 m3, and will be completed in 1994/95. The Second Stage will involve: —